S High St

E Bowery St to Church St

Starts: August 29, 2022
Ends: November 18, 2022

Limited Access

Kenmore Construction Co. and Akron Energy Systems have closed the west half of the S. High St. and Church St. intersection as they continue to work on the construction of a steam vault and service line that will be crossing S. High St.
Traffic will continue to be maintained on S. High St. during this work but merged into a single lane around the work zone. Drivers wanting to reach Church St. will be detoured using S. High St., University Ave. and S. Main St.
The first phase of this project on the west side of the street is expected to be completed by Tuesday, October 4, and the remaining work on the east side is then planned to start and continue through Friday, November 18.