Mill St to Martin Luther King Jr Blvd
Starts: October 2020
Ends: May 2022
Project Description
Full improvements including full depth asphalt pavement, concrete curbs and walks, cycle track, landscaping, permeable pavers, traffic signalization, lighting and other aesthetic items. Also includes utilities: Ohio Edison, AT&T, and sewer conduits and manholes.
Anticipated Maintenance of Traffic
One lane of traffic in each direction will be maintained at all times.
Dollar Value of Project
$15,967,702.96
Benefits to Akron Upon Completion of Work
This project will complete the transformation of Akron’s downtown Main Street corridor into a space that will accommodate all users, as well as provide well maintained infrastructure and greener solutions for water runoff management.