Vernon Odom Boulevard

@ I-77

Starts: August 15, 2018
Ends: August 22, 2018

Traffic Maintained

Team Fishel and MCI Metro plan to begin conduit installation along the south side of Vernon Odom Blvd., beneath the 1-77 overpass, on Wednesday, August 15.
Traffic will be maintained at all times, but drivers are urged to use caution as the work zone may need to occasionally be shifted as work is being completed.
This project is planned to be completed by Wednesday, August 22.