Traffic Alerts

Dayton Street

E Cuyahoga Falls Ave to E Tallmadge Ave

Starts: December 2, 2019
Ends: January 24, 2020

Traffic Maintained

H.M. Miller Construction Co. and the City of Akron Water Department continue the replacement of lead water services along Dayton St., between E. Cuyahoga Falls Ave. and E. Tallmadge Ave.
Lane closures will be needed during the day, but flaggers will be on site to maintain traffic at all times.
This work is expected to be complete by Friday, January 24, 2020.
Beginning at 9am on Monday, December 9, the contractor plans to close the road to all thru traffic between E. Cuyahoga Falls Ave. and Hillier Ave. as they work to replace an existing hydrant located in front of 813 Dayton St. N. Main St. or Patterson Ave. can be used as alternate routes during this closure. This portion of the project is expected to be complete by 3:30pm.