Cuyahoga Street

North and South of Peck Rd

Starts: May 20, 2019
Ends: September 6, 2019

Traffic Maintained

H.M. Miller Construction Co. and the City of Akron continue sewer work along Cuyahoga St., near Peck Rd.
The full project extends from 800 feet north of Peck Rd. to 2500 feet south of it, but it will involve a shorter work zone that will shift as work is being completed. A single lane will be maintained at all times during this work by the use of portable traffic signals.
Drivers are urged to use caution while driving through this area and encouraged to use an alternate route when possible as there may be long delays.
This work is expected to be complete by September 6.