Projects

Mayfield Avenue Sewer Improvements

Twin Oaks Rd, W Market St, N Portage Path

Starts: April 2019
Ends: October 2019

Project Description

The project consists of cured in place pipe lining of 2822 linear feet of sanitary sewer and 928 linear feet of storm sewer. It will also consist of construction of 361 linear feet of 8 inch sanitary sewer along Maplewood Avenue. Manhole replacement, reconstruction and rehabilitation will also occur throughout the project limits.

Anticipated Maintenance of Traffic

Partial/temporary street closures will occur in certain directions for equipment moving. Local and emergency access will be maintained throughout construction period.

Dollar Value of Project

$526,065.28

Benefits to Akron Upon Completion of Work

This project will help mitigate inflow and infiltration problems in the Mayfield Avenue Sewer Area. The new sewer on Maplewood Avenue will provide more flow through the sanitary sewers and prevent back-ups from occurring.