Project Name:Starts:Ends:More Info
Akron Innerbelt (SR59) Oak Park Renewal
Dart Ave and Rand Ave
May 2016August 2018View Project
Brittain Road Sidewalk
E Tallmadge Ave to Independence Ave
August 2018September 2018View Project
Chittenden Green Project CSO Rack 3
Bittaker St - Chittenden St to Ardella Ave
September 2018April 2019View Project
City of Akron 2018 Resurfacing Program
Locations throughout the city
June 2018November 2018View Project
Evans Avenue Bridge
Home Ave to 400' east of Shreve Rd
September 2018July 2020View Project
Exchange Cedar Signalization
Exchange St and Cedar St between S Portage Path and S Broadway St
September 2016October 2018View Project
Firestone Business Park
Cole Ave @ S Main St to west
September 2018March 2019View Project
Hampton Ridge Sanitary Sewer
Hampton Ridge Dr to Sand Run Pky
July 2018November 2018View Project
Hands on Exchange
Arc Dr to Route 8
August 2018August 2018View Project
I-76/I-77 Main Broadway Interchange
I-76/I-77 interchange at S Main St and S Broadway St
July 2016July 2020View Project
Main Street Corridor
Market St to Exchange St
July 2018October 2020View Project
Mayfield Avenue Sewer Improvements
Twin Oaks Rd, W Market St, N Portage Path
May 2019September 2019View Project
Ohio Canal Interceptor Tunnel
North of Mustill Store near Hickory St to W Exchange St
November 2015July 2019View Project
Old Main Sewer Separation CSO Rack 21
Intersection of Beech St and N Howard St
December 2016September 2018View Project
Safe Routes to Schools 2015
Vernon Odom Blvd - Ruth Ave to Rhodes Ave
May 2018August 2018View Project
Safe Routes to Schools 2016
E Exchange St - Goodkirk Rd to S Arlington St, Wilbeth Rd - 1-77 to S Arlington St
August 2018November 2018View Project
Sanitary Sewer Reconstruction 2016
Locations throughout the city
February 2017September 2018View Project
Sanitary Sewer Reconstruction 2017
Locations throughout the city
October 2018October 2019View Project
Signal Improvements and Coordination
Brittain Rd, Copley Rd, E Tallmadge Ave, W Market St
April 2017August 2018View Project
Sourek Road Pump Station Replacement
2545 Sourek Rd
January 2019October 2019View Project
SUM SR18 Hawkins to Portage Path
W Market St - Hawkins Ave to Portage Path
October 2017August 2018View Project
White Pond Water and Sewer Extension
White Pond Dr, Scudder Dr, Logan Dr, Auten Dr
November 2017October 2018View Project